Construction Update
Posted by Salish Seaside RV Haven on
As of today all the major services are installed, both mains and to individual pads: sewer, water, gas. Electrical and communications conduit are going in next. The foundation for the amenity building is ready to pour concrete and then the framing can start. The sewer lift station will be delivered on Tuesday. Although a tremendous amount of work has been done, looking at the site there's little to show for it just because it's all underground. C'est la vie.